| Task Priority | Task Name | Start Date | Task Duration (Days) | Completion | Assigned to | Notes |
|---|---|---|---|---|---|---|
| Normal | Review | 2006-11-28 | 4 | 10% | User1 User2 |
Review the project management solution |
| Normal | Trial | 2006-12-04 | 5 | 0% | User1 |
Run a test project to see how well this application copes |
| Normal | Conclude | 2006-12-11 | 1 | 0% | User1 User2 |
Conclude if this application is up to the task |
| Resource | Phone | |
|---|---|---|
| User1 | [email protected] | 01234 567890 |
| User2 | [email protected] | 01234 567890 |